Makespan - Production Planning & Scheduling Solutions Ltd.                                

HomeSequencing EffectWhy EFAEFA AlgorithmCasting Plant PCB PlantPartnersContact Us


The Effect of Sequencing Jobs on Total Lead Time

 

Table-1

PROD’

QTY

M1

M2

A

5

20

10

B

5

10

20

In order to explain the sequencing effect on the total lead time let’s take a simple example: Two products A and B are manufactured by two machines M1 and M2 in the order M1M2. The quantity and process time per item (in minutes) are given in Table-1. In order to simplify the example we assume zero setup times and identical priority for the two batches. There are two possible sequences AB and BA.
The Gantt chart of the two sequences is shown in the chart below.

 

We can see that the total lead-time of sequence  BA at the bottom side is 160 minutes, while the total lead time of sequence AB, at the upper side of the chart is 210 minutes (31% more). The reason lies in the different wait/waste time (green sections) of Machine M2. Machine M2 can start processing an item only after machine M1 had finished it, see the processing schedule of any item (1, 2, 3, 4, 5) by machine M1 and then by machine M2. In sequence AB machine M2 is forced to wait 60 minutes: either 20 minutes for the first item and 10 minutes for each of the other 4 items of product A (as seen in the chart) or  wait for 60 minutes and then process the five items continuously. While in sequence BA machine M2 is forced to wait only 10 minutes (for the first item of product B). This simple example shows the sequencing effect on the total lead time. The main cause is the variation of process parameters  between product A and B.

 

 In a real shop floor environment the situation is more complicated, there are many parameters which affect the total lead time for example:

- Many work centers, each one with one machine or more.

- The products can have several different parameters such as process times, setup times,
   common setup etc.

- The jobs can have different quantities, delivery dates etc.

 

The result of poor sequencing is low efficiency of the production line, long lead times and more jobs in process. Hence the ability to accept customer orders with short delivery dates is decreasing.

 

back

 

Home Sequencing Effect Why EFA EFA Algorithm Casting Plant PCB Plant Partners Contact Us